01. Starting a New Project (Free Preview)

This is a preview lesson. Please purchase the course to access all lessons.

Welcome to the course!

This course is delivered in 3 iterations. Each of them reviews PRINCE2® from a different perspective and adds more detail by building on top of the previous one.
This is the first iteration; the shortest, and the simplest one. There are only 5 lessons here to give you an overall understanding of the methodology. You don’t have to remember everything that is discussed here; they will be reviewed again in the next iterations.

Most lessons contain videos similar to the one below. After you click on the video to play it, there will be 3 features on the bottom-right corner of it that may be interesting to you:

  • Making it full screen
  • Increasing or decreasing the playback speed
  • Adding subtitle (the CC button)

Enjoy the course :)


Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS. All rights reserved.

So far, we’ve talked about starting up a project. What do you think should be done next?

 

Quiz

  1. Each project has a trigger. What do we call this trigger in PRINCE2?
  2. What topics are usually covered in the trigger?
  3. What’s the name of the highest role in the project, who is responsible for the return of investment?
  4. What are the two main outputs of starting up a project? What topics are covered in them?
  5. What’s the first Project Board decision about?

Answers

  1. Project mandate
  2. Project mandate contains very high-level information about the purpose of the project, as well as its scope, quality, cost, and benefits. Remember that it’s a very simple document.
  3. Executive
  4. One is the Project Brief, that covers general information about the project (reasons, scope, quality, cost, benefits, and team structure), and the other is our plan for the next stage.
  5. The check the Project Brief to see if it’s a good idea to proceed with this project.

Back to: PRINCE2® Foundation, 2017 Edition